农村公路“三年行动计划”乡村通畅工程是省政府重点民生工程,又是市政府为民要办的“十件实事”之一。为加快推进农村公路“三年行动计划”建设,确保圆满完成建设任务,市交通运输局对2016年农村公路“三年行动计划”开工情况进行了督导,具体通报如下:
桥梁项目开工情况排序县(区)计划情况开工情况开工率(%)座延米座延米合计2217520.31134330.851.13%1宁陵县24676.324676.3100.00%2梁园区2066620666100.00%3示范区4193.54193.5100.00%4睢阳区2197121971100.00%5夏邑县1656416564100.00%6柘城县23122321108891.30%7睢 县411337.5717217.07%8虞城县27848000.00%9民权县451041000.00%
村道项目开工情况排序县(区)计划情况开工情况开工率(%)个数里程个数里程合计5441067344659.761.83%1柘城县47123.147123.1100.00%2宁陵县75119.175119.1100.00%3示范区2145.92145.9100.00%4夏邑县98156.595151.596.81%5民权县47109.5378678.54%6睢阳区65131.13062.247.44%7梁园区4583.32132.939.50%8睢 县61127.5183930.59%9虞城县85171000.00%
县乡道项目开工情况排序县(区)计划情况开工情况开工率(%)个数里程个数里程合计95511.482459.489.83%1柘城县765.7765.7100.00%2宁陵县2468.82468.8100.00%3民权县550.3550.3100.00%4示范区315.2315.2100.00%5夏邑县1495.71495.7100.00%6睢阳区1362.31362.3100.00%7梁园区851.1851.1100.00%8睢 县850.3850.3100.00%9虞城县1352000.00%